Nordsee One two turbines from completion

Nordsee One two turbines from completion

01-09-2017 10:00:00


The turbine installation phase of the 332 MW Nordsee One wind turbine project in the German part of the North Sea is approaching completion as 52 of 54 Senvion 6.2 MW turbines are in place. This is stated by Reetec, one of the companies involved in the project.

On behalf of Senvion, SSC Wind and Reetec install the 54 turbines on the Nordsee One wind farm, located about 40 kilometers from the island of Juist. The first Senvion 6.2M126 turbine was installed by MPI Offshore's jack-up MPI Enterprise in early March.

The turbines are gradually transported from Bremerhaven via Eemshaven to the installation site, which has water depths between 26 and 29 meters. The installation and commissioning of all 54 wind turbines is expected to be completed by the end of 2017.

Source: Offshore Wind / Maritime Denmark


Klik venligst

< Front page

Copyright © Maritime Denmark



Breaking News

- Ørsted buys Lincoln Clean Energy
- Better things ahead for drilling rigs
- Danish Maritime Fair: Seeking new horizons
- Denmark’s days as oil exporters are over
- Norsok approved for submersible drilling rig
- Jesper R. Olsen new CFO of Maersk Drilling
- Horn Rev 3’s first wind turbine installed
- Maersk Drilling secures two contract
- Maersk and Vestas join forces
- Maersk Decom mangagement in place
- Transocean are scrapping four deep-sea rigs
- Semco Maritime receives important order


Todays Top 5

- Maersk board of directors adds member
- Tuco receives order for Multi-Mission boats


This weeks Top 10

- Shippingcompanies are going against Rønne
- Alba Rousing breaks free
- Lindø Port of Odense result decrease
- Molslinjen in financial battle with Rønne
- Shippingcompanies are going against Rønne
- Maersk board of directors adds member
- Tuco receives order for Multi-Mission boats
Klik venligst
Klik venligst
Klik venligst
Klik venligst